Winterization support for IDPs at sites


In effort to provide witnerized to the earthquake victims in displacement sites, IOM is carrying out winterization kit distribution on two phases. Currently Phase I distribution is being carried out and will  be completed by January 9.

Below is the detail from the first phase distribution:

 

District No of kits Blanket Tarps Rope Cash Total Kgs Total Volume (m3) First phase distribution date
Dhading 1277 2350 2554 4700 957750 61518.4 231.533504 5th,6th &7th Jan
Gorkha 1263 1374 916 0 3435000 8060.8 119.2241  
Sindupalchowk 882 2646 1764 1764 6615000 1552.32 60.06816 31st Dec, 1st, 2nd ,3rd Jan
Kavrepalachok 65 195 130 130 487500 1144 4.472 28th Dec
Makwanpur 59 177 118 70 442500 1038.4 4.0592 29th Dec
Nuwakot  69 54 36 0 517500 316.8 1.2384 1st Jan
Ramechapp 58 174 116 68 465000 1020.8 3.9904 31st Dec
Rasuwa 850 2550 1700 1700 6375000 14960 58.48 31st Dec, 1st Jan
Dolkaha 154 462 308 308 1972500 2710.4 10.5952 5th,6th &7th Jan
                 

Planning for 2nd Phase distribution is being carried out. Due to the border blockade and fuel shortage, the distribution is delayed.